Course Curriculum

UNIT1.Microsoft Project - Introduction
UNIT1.Microsoft Project – Introduction 00:05:00
UNIT2.Microsoft Project - Task Creation
UNIT2.Microsoft Project – Task Creation 00:07:00
UNIT3.Microsoft Project - Predecessors
UNIT3.Microsoft Project – Predecessors 00:05:00
UNIT4.Microsoft Project - Types of Predecessors
UNIT4.Microsoft Project – Types of Predecessors 00:08:00
UNIT5.Microsoft Project - General Options I
UNIT5.Microsoft Project – General Options I 00:05:00
UNIT6.Microsoft Project - General Options II
UNIT6.Microsoft Project – General Options II 00:07:00
UNIT7.Microsoft Project - Cusomize RibbonNOT
UNIT7.Microsoft Project – Cusomize RibbonNOT 00:06:00
UNIT8.Microsoft Project - Work Breakdown Structure
UNIT8.Microsoft Project – Work Breakdown Structure 00:09:00
UNIT9.Microsoft Project - Work Breakdown Structure Naming Convention
UNIT9.Microsoft Project – Work Breakdown Structure Naming Convention 00:05:00
UNIT10.Microsoft Project - Recurring Tasks
UNIT10.Microsoft Project – Recurring Tasks 00:04:00
UNIT11.Microsoft Project- Creation of Calendar
UNIT11.Microsoft Project- Creation of Calendar 00:04:00
UNIT12.Microsoft Project- Assigning of Calendar
UNIT12.Microsoft Project- Assigning of Calendar 00:03:00
UNIT13.Microsoft Project- Creation _ Assigning of Task Calendar
UNIT13.Microsoft Project- Creation _ Assigning of Task Calendar 00:04:00
UNIT14.Microsoft Project- Partial predecessors
UNIT14.Microsoft Project- Partial predecessors 00:04:00
UNIT15.Microsoft Project- Critical Tasks
UNIT15.Microsoft Project- Critical Tasks 00:03:00
UNIT16.Microsoft Project- Status Bar
UNIT16.Microsoft Project- Status Bar 00:04:00
UNIT17.Microsoft Project- Project Information Tool
UNIT17.Microsoft Project- Project Information Tool 00:05:00
UNIT18.Microsoft Project- Contextual menu
UNIT18.Microsoft Project- Contextual menu 00:04:00
UNIT19.Microsoft Project- Milestones and Estimated Tasks
UNIT19.Microsoft Project- Milestones and Estimated Tasks 00:05:00
UNIT20.Microsoft Project- Opening and Closing of Project
UNIT20.Microsoft Project- Opening and Closing of Project 00:04:00
UNIT21.Microsoft Project- Notes
UNIT21.Microsoft Project- Notes 00:05:00
UNIT22.Microsoft Project- Mini Tool Bar
UNIT22.Microsoft Project- Mini Tool Bar 00:03:00
UNIT23.Microsoft Project- Early Start _ Early finish and Late Start _ Late finish
UNIT23.Microsoft Project- Early Start _ Early finish and Late Start _ Late finish 00:03:00
UNIT24.Microsoft Project- Slack
UNIT24.Microsoft Project- Slack 00:03:00
UNIT25.Microsoft Project- Task Constraints
UNIT25.Microsoft Project- Task Constraints 00:06:00
UNIT26.Microsoft Project- Task Constraints-2
UNIT26.Microsoft Project- Task Constraints-2 00:07:00
UNIT27.Microsoft Project- Task Constraints 3
UNIT27.Microsoft Project- Task Constraints 3 00:03:00
UNIT28.Microsoft Project- Link_Unlink Tasks
UNIT28.Microsoft Project- Link_Unlink Tasks 00:04:00
UNIT29.Microsoft Project- Activate_Inactivate Tasks
UNIT29.Microsoft Project- Activate_Inactivate Tasks 00:03:00
UNIT30.Microsoft Project- Sharepoint Sync
UNIT30.Microsoft Project- Sharepoint Sync 00:03:00
UNIT31.Microsoft Project- Use of templates
UNIT31.Microsoft Project- Use of templates 00:03:00
UNIT32.Microsoft Project- Moving Tasks
UNIT32.Microsoft Project- Moving Tasks 00:06:00
UNIT33.Microsoft Project-Timeline
UNIT33.Microsoft Project-Timeline 00:04:00
UNIT34.Microsoft Project-Defining Resources
UNIT34.Microsoft Project-Defining Resources 00:07:00
UNIT35.Microsoft Project-Assigning Resources
UNIT35.Microsoft Project-Assigning Resources 00:04:00
UNIT36.Microsoft Project-Resource Calendar
UNIT36.Microsoft Project-Resource Calendar 00:03:00
UNIT37.Microsoft Project-Project Baseline
UNIT37.Microsoft Project-Project Baseline 00:03:00
UNIT38. Microsoft Project-Cost
UNIT38. Microsoft Project-Cost 00:03:00
UNIT39.Microsoft Project-Update Project Progress
UNIT39.Microsoft Project-Update Project Progress 00:04:00
UNIT40.Microsoft Project-Project Tracking
UNIT40.Microsoft Project-Project Tracking 00:05:00
UNIT41.Microsoft Project-Earned Value Analysis
UNIT41.Microsoft Project-Earned Value Analysis 00:06:00
UNIT42.Microsoft Project-Earned Value Analysis-II
UNIT42.Microsoft Project-Earned Value Analysis-II 00:03:00
UNIT43.Microsoft Project-Update Tasks I
UNIT43.Microsoft Project-Update Tasks I 00:05:00
UNIT44.Microsoft Project-Update Tasks II
UNIT44.Microsoft Project-Update Tasks II 00:05:00
UNIT45.Microsoft Project-Update Tasks III
UNIT45.Microsoft Project-Update Tasks III 00:04:00
UNIT46.Microsoft Project-Cost Analysis
UNIT46.Microsoft Project-Cost Analysis 00:04:00
UNIT47.Microsoft Project-Resource Analysis
UNIT47.Microsoft Project-Resource Analysis 00:05:00
UNIT48.Microsoft Project-Resource Leveling I
UNIT48.Microsoft Project-Resource Leveling I 00:06:00
UNIT49.Microsoft Project-Resource Leveling
UNIT49.Microsoft Project-Resource Leveling 00:05:00
UNIT50.Microsoft Project-Task Inspector I
UNIT50.Microsoft Project-Task Inspector I 00:04:00
UNIT51.Microsoft Project-Task Inspector II
UNIT51.Microsoft Project-Task Inspector II 00:05:00
UNIT52.Microsoft Project-Slippage
UNIT52.Microsoft Project-Slippage 00:05:00
UNIT53.Microsoft Project-Filtering
UNIT53.Microsoft Project-Filtering 00:03:00
UNIT54.Microsoft Project-Grouping
UNIT54.Microsoft Project-Grouping 00:03:00
UNIT55.Microsoft Project-Highlightling
UNIT55.Microsoft Project-Highlightling 00:04:00
UNIT56.Microsoft Project-Use of Tables
UNIT56.Microsoft Project-Use of Tables 00:05:00
UNIT57.Microsoft Project-Earned Value Analysis III
UNIT57.Microsoft Project-Earned Value Analysis III 00:06:00
UNIT58.Microsoft Project- Calendar, Gantt Chart _ Network Diagram View
UNIT58.Microsoft Project- Calendar, Gantt Chart _ Network Diagram View 00:05:00
UNIT59.Microsoft Project- Resource Sheet, Usage _ Form View
UNIT59.Microsoft Project- Resource Sheet, Usage _ Form View 00:05:00
UNIT60.Microsoft Project- Resource Graph and Name Form View
UNIT60.Microsoft Project- Resource Graph and Name Form View 00:05:00
UNIT61.Microsoft Project- Task Usage, Form _ Sheet Views
UNIT61.Microsoft Project- Task Usage, Form _ Sheet Views 00:04:00
UNIT62.Microsoft Project- Team Planner, Timeline _ Tracking Gantt View
UNIT62.Microsoft Project- Team Planner, Timeline _ Tracking Gantt View 00:05:00
UNIT63.Microsoft Project- New Chart Reports
UNIT63.Microsoft Project- New Chart Reports 00:06:00
UNIT64.Microsoft Project- New Table Report
UNIT64.Microsoft Project- New Table Report 00:04:00
UNIT65.Microsoft Project- New Comparison Report
UNIT65.Microsoft Project- New Comparison Report 00:07:00
UNIT66.Microsoft Project- Cost Reports
UNIT66.Microsoft Project- Cost Reports 00:06:00
UNIT67.Microsoft Project- Resource Reports
UNIT67.Microsoft Project- Resource Reports 00:04:00
UNIT68.Microsoft Project- In- Progress Reports
UNIT68.Microsoft Project- In- Progress Reports 00:05:00
UNIT69.Microsoft Project- Report organizer
UNIT69.Microsoft Project- Report organizer 00:04:00
UNIT70.Microsoft Project- Project Help
UNIT70.Microsoft Project- Project Help 00:03:00
  • PRIVATE
  • 10 Days
  • 70 Units
  • 5 hours, 24 minutes Hrs

Select Your Currency

WOOCS 1.1.8
Drop Us A Query
[contact-form-7 id="5639" title="Drop Us A Query"]
© 2016, ALL RIGHTS RESERVED.
Create an Account